The Staenberg Group

Mega developments redefine St. Louis region's landscape

Mega developments redefine St. Louis region's landscape

Feature photo credit: Drew Edelstein.

Panelists sum up Chesterfield Valley comeback

Panelists sum up Chesterfield Valley comeback

October CCIM-STL panelists included (L to R): Mike Geisel, Bob Nation, Emily Ackley and Natasha Das. Photo credit: MWM STL

The Staenberg Group begins $70 million Metro East development

The Staenberg Group begins $70 million Metro East development

The featured site plan from the developer, The Staenberg Group, shows the location of the outlots, retail space and a Menards in the Glen Carbon, Ill. retail development Orchard Town Center. Image credit: The Staenberg Group.

Live events return for STL CRE associations

Live events return for STL CRE associations

St. Louis fire chief Dennis Jenkerson (right) accepts donation to Cool Down St. Louis from incoming IFMA-SL president Dave Gardin (left) and immediate past president Scott Held (center). Photo courtesy IFMA-SL.

Ready to rock-n-roll at The District in Chesterfield

Developers of The District commercial project are pumped up about Chesterfield, Mo's newest development, as expressed in a recent CREW St. Louis webinar and virtual tour last month.

More than 50 attendees tuned in to learn about the project, described by CREW-SL as a one-stop destination of entertainment — a hub for playing, eating and rocking [that] is powered by The Staenberg Group (TSG Properties), a local real estate development firm who designs, develops and manages shopping centers throughout the United States.

TSG Properties engages in communities through pro-bono consulting, direct philanthropic gifts and volunteering technical expertise to make neighborhoods stronger, healthier and more sustainable.

“Everybody remembers the flood with 11 feet of water that led to the project,” said Michael Staenberg, president of The Staenberg Group.

His company bought The Commons, then the longest strip mall in the U.S. at 2 miles and 2 million SF, from the Todman brothers.

“The Todman brothers realized that two outlet malls in Chesterfield wouldn’t work, so they had to come up with a new strategy,” added Timothy Lowe, TSG’s vice president of leasing and development. 

“The name came from early conversations about a music venue and entertainment district,” Staenberg said. “We’re keeping it simple and easy to remember.”

The project is proof that “retail is emerging, not dead,” he noted. The site encompasses 400,000 SF and the final built space will be 200,000–250,000 SF.

“We thought we could create something unique to St. Louis. There’s nothing like it anywhere in the country. It will have entertainment for all segments of the area.”

“We never intended to develop The District in one phase,” Lowe said. “It will start with Topgolf followed by Main Event Entertainment, with bowling, rope tag, pool tables, laser tag and more, as “barbells” or anchors.”

The Factory section will be a music venue, at 58,000 SF and a seating capacity of 3,000.

“We asked artists what they want,” Staenberg said. “This will allow artists to have an intimate experience and still attract a good crowd. It will be a multipurpose function without short-changing the music.”

Features include adequate parking, high security, easy access, comfortable seats, and top-notch sound and lighting. Events will be cashless, but ATMs will provide attendees access to cash so artists can sell their own merchandise at concerts.

“We’ve made great strides with the number of bars, restrooms, green rooms, truck access — every nuance we could think of,” he said. “We thought about everything to make the customer experience exceed expectations.” 

According to Brian Carp, COO of The Factory and moderator of the CREW-SL event, “The Factory will be a completely different experience. We’ll be able to use some of the existing buildings, which provides flexibility, and will have 2,100 to 2,500 parking spaces at a 7:1 ratio.”

Carp said the plan is to bring in restaurants that are new to the area rather than duplicate those at Chesapeake Commons.

To date, the exterior has been painted. Phase II involves building “that front door, a place to gather” called the Pavilion, with outdoor seating for surrounding restaurants and a stage.

Phase III will feature a 90,000 SF footprint for “experiences” or outdoor activities such as pickleball, sand volleyball and more.

In response to community input, the District will include a sit-down restaurant that will accommodate 650 for nonprofit organization events.

“We’ve been approached by 20 nonprofits to hold charitable events,” Staenberg said.

Phase III will depend on users and could take three to four years to complete.

The west side of the complex will feature parking.

The space would have already opened if not for the COVID-19 pandemic, and July 2021 is now the hoped-for drop date.

Other challenges included “a number of battles to get zoning in place,” recalled Michael Doster of Doster Ullom & Boyle, land use attorney for TSG.

“One problem was signage: Electronic message boards were prohibited, as well as lights and the height we wanted, but you need signage and it has to be big to be effective.”

“The electronic sign was important so people could drive by and see who’s playing,” Staenberg explained.

Lowe called The District and The Factory a chance to put all entertainment use into one place and create a dynamic area that can attract people from all around the area.

Among the decisions as the project evolved was not to include office space.

Looking ahead

Asked about the future, Staenberg said retail had changed even before the pandemic and that traditional huge malls will be torn down.

“People want experiences and a place to hang out. Malls don’t have entertainment and sociability. People like smaller shops. We’ll have to figure out what to with the rest of them, such as converting to residential use.”  

“We are being very selective and are patient — this is a 10-year project. It isn’t going to be sold and we won’t flip it. The District is just magnificent. We thank our partners — we have the A Team!”

Read previous, related MWM article here from October 2020: Current Chesterfield development on par with 2019

Current Chesterfield development on par with 2019

This week’s CCIM St. Louis Metro Chapter virtual luncheon presentation provided solid insight to the development of the Chesterfield, Mo. area.

With presentations from Mike Geisel, city administrator with the City of Chesterfield; Tim Lowe, VP of leasing and development with The Staenberg Group; and Jeff Tegethoff, operating partner of CRG, attendees received a comprehensive look at the future of the city.

Geisel started the presentation by introducing “Envision Chesterfield,” the city’s comprehensive plan completed through a 21-month process which was adopted in September of this year.

Data shows that the city of Chesterfield has grown at 2.6 times the rate of inflation. With 44 active development projects, the city is on par with 2019 numbers despite the challenges of 2020.

“In the last ten years, we’ve seen 2,300 residential units being developed. We’ve seen 3.9 million SF of commercial development and 650,000 SF of industrial development,” Geisel said.

The District and Wildhorse developments are two large components contributing to the current success in Chesterfield, according to Geisel.

Working from the opportunity of their neighboring tenant TopGolf, The Staenberg Group is developing The District - previously an old outlet mall - into a new entertainment area. The revitalization has recently handed over the 48,000 SF shell to their new tenant, Main Event, set to open in June 2021.

On the other end of the property, The Factory, the first built-from-the-ground-up live music venue in the Midwest in more than 20 years, is currently underway. Lowe acknowledged the risk of this type of facility in the current COVID climate, but also noted the high demand from both fans and bands.

“We’re excited. This is going to be a unique draw to the area. They’re planning to open in May of next year. While the current guidelines would not allow The Factory to open and be successful, the good news is that there is a lot of pent-up demand for next year. We are hoping the rules of engagement in 2021 will allow us to open and be functional,” Lowe said.

Phase 2 of The District will feature an open-entrance, steel structured pavilion which will serve as an eye-catching anchor of the development.

“We have a lot of work to do to figure out what goes under the pavilion, but (we) will have grass, fire pits and outdoor seating. It’s a neat area within the development that allows people to read books, play with their kids, things like that,” Lowe said.

The final phase of The District is currently being planned. At this point, potential activities include indoor and outdoor pickleball, sand volleyball and eSports.

Lowe also mentioned the Chesterfield Mall, which The Staenberg Group is currently working on a master plan to convert the property into an urban downtown development. The plan includes housing, office, retail, and restaurants, and is scheduled to be completed and presented to the city by the end of the year.

Tegethoff also shared his vision for the existing Wildhorse project and Wildhorse Village. Wildhorse has scheduled openings throughout 2021, including the 188-residential spaces in March and the AC Hotel by Marriott in December. The notable, 15,000-SF Ruth Chris Steak House opens in two-weeks.

Wildhorse Village, an 80-acre development to include 1 million SF of office space, more than 500-residential units and 100,000 SF of restaurant and retail space, is currently underway. The project will not be phased and anticipates openings as early as 2023.

“We never really thought about phasing Wildhorse Villiage. The momentum of early interest in the sub lots enabled us to do it all at one time,” Tegethoff said.

“We feel like there has never been a more exciting time to developing in Chesterfield.” Tegethoff said.

Despite the challenges of 2020, the city of Chesterfield is on the rise.

to view the entire program, please visit CCIM St. Louis’s LinkedIn page.